4th Av N Specific Plan passes muster with Planning Commission on consent agenda



While the Planning Commission still has to hold a public hearing on the SP plan slated for 1614/1616 4th Av N, they gave preliminary unanimous approval last week for via their consent agenda (which is a slate of proposals voted on as a whole; unless individual plans are pulled off the consent agenda, they are voted on without discussion). If the plan survives the public hearing stage and gets final approval from the commission, it will go to Metro Council as recommended by planning and only needing a simple majority for council approval.

There are several conditions this plan has to meet, according to the Planning Department, including fire code requirements and a Public Works requirement to remove striping from parking spaces in the row. Here is Planning's recommendation:

STAFF RECOMMENDATION
Staff recommends approval with conditions and disapproval without all conditions as it is consistent with the North Nashville Community plan and meets several critical planning goals.

CONDITIONS
1. Use in the SP is limited to up to 7 residential units.
2. For any development standards, regulations and requirements not specifically shown on the SP plan and/or included as a condition of Council approval, the property shall be subject to the standards, regulations and requirements of the RM15 zoning district as of the date of the applicable request or application.
3. Minor modifications to the preliminary SP plan may be approved by the Planning Commission or its designee based upon final architectural, engineering or site design and actual site conditions. All modifications shall be consistent with the principles and further the objectives of the approved plan. Modifications shall not be permitted, except through an ordinance approved by Metro Council that increase the permitted density or floor area, add uses not otherwise permitted, eliminate specific conditions or requirements contained in the plan as adopted through this enacting ordinance.
4. The requirements of the Metro Fire Marshal’s Office for emergency vehicle access and adequate water supply for fire protection must be met prior to the issuance of any building permits.

If you want to read the rest of their analysis, it starts on page 74 here.

I have not perceived any changes that Salemtown Neighbors Neighborhood Association is asking developers to make, so I would be surprised if anyone shows up at the public hearing to address the plan. The developers met with the association in October. Barring any surprises, this plan will probably breeze through the commission and Metro Council.