Revolving sticker shock: unforecasted costs of Music City Center keep rising

I agree [the risk to other Metro services is] the downside of [building a new convention center]. But it's not the thing you go out there and tell people.
--Music City Center chair Ron Samuels in 2009


Despite our red-flag-waving common sense that projected costs for capital projects have a tendency to be low-balled for the sake of selling those projects to a reluctant audience, those of us who questioned Mayor Karl Dean's plan to embark on the largest capital project in Nashville history were scolded for our "negativism". I'm wondering whether Ron Samuels thinks now that it is okay to talk about skyrocketing expenses:

The cost to run the Music City Center in its first fiscal year of operation will be about $4 million more than previously projected, according to a budget approved by Convention Center Authority members on Thursday.

The increase is linked to the expected doubling of the Music City Center’s projected utility bill, which is estimated to total $5.3 million from July 2013 to June 2014. The authority had been working under the assumption that it would pay about $2.5 million in utilities in that one-year period, based on a demand and feasibility study of the Music City Center project generated by hospitality consulting firm HVS in 2010 ....

The variance exists because the HVS study was conducted around a building that had not yet been built, said Nashville Convention Center Executive Director Charles Starks, while the more recent number includes newer estimates from Nashville Electric Service and District Electric Service using more accurate information about the 1.2 million-square-foot building.

Remarkable that unflinching MCC spokesperson Holly McCall was not trotted out again to point fingers at Metro Council (and the constituents whom they represent) for the latest bad news. The traction to that rationalization must be missing.

The revenues to meet these obligations have to come from somewhere, and I doubt the bigshots in the tourism industry are going to take up a collection among themselves to bridge the gap between fairy tale and balance sheet. Besides, they have future election campaigns to finance.

Nashville broke ground on this big box and we bought it. And those of us who were realistic and didn't lose ourselves in the wet dreams of Music City Center boosters were right. Now we can only hope and pray that their fantasies will not continue to endanger the General Fund paying for most of what the people who actually live here enjoy.

Friday, September 21, 2012

Cancelled conventions at Music City Center cost Nashville

Nashville is already shelling out $678,000 in taxpayer dollars to cover the losses of two conventions originally booked for the new, historically expensive Music City Center. Crane Watchdog culls the details:

Two associations, the Hearth, Patio & Barbecue Association (HPBA) and the Technology & Maintenance Council of the American Trucking Association (ATA) were scheduled to hold conferences at the center more than a month before the building was scheduled to open ....

Now the associations have made the decision to relocate upon news that construction will not be fully completed before their events. Of the two shows, one will remain in the area while the other has relocated to Florida. Aside from the tourism loss ... that the government is paying "more than $678,000 in taxpayer dollars to make restitution" to the two associations.

The payout approval is also documented in the July 12, 2012 Convention Center Authority meeting minutes. The minutes confirm the payment amount demonstrating that the Authority will pay the ATA $110,000 and also reduce the rent for future convention in the years 2015-2017 from $35,000 per year to $0.00 per year. In addition, the minutes show the Authority must pay $568,153 to the HPBA. All of these fees cover a cancellation fee, assist the groups with other expenses necessary for relocation, and cover additional expenses that would not have been necessary if the events had remained at the Music City Center.


However, convention center spokesperson Holly McCall essentially puts the blame on the Metro Council for the unplanned expenses:


The Music City Center isn't scheduled to open before May 2013, so why did the center agree to book them a month before?

"These shows were booked back in June of 2009," said McCall. "That's when metro council originally looked at voting on the convention center. They ended up not voting on the convention center until January 2010, which set us back 7 months."


So, it's Metro Council's fault that convention center planners and schedulers took council approval for granted even though popular opinion was not strongly in favor of building it? According to the Metro Charter, council approval is part of the procedure for approving capital projects. It is not something that unexpectedly pops out of left field.

Rather than blaming the Metro Council, perhaps Ms. McCall should have pointed to the failures of the agency she represents for not planning some cushion for the probability that delays might occur in the council approval process.  The convention center authority should own the missteps in the timeline that caused them to fail to account for the messiness of public process. My guess is that the convention center leaders in 2009 were willing to risk the loss of individual conventions and public money for the immediate PR projection of inevitability that the claim "Conventions are already being booked!" was giving them.

The Metro Council can be ineffectual enough, but for convention center leaders to make them scapegoats for their own wasteful messes is cowardly and shameful.

Saturday, July 23, 2011

A promise Convention Center Authority PR Manager Holly McCall could not keep


This project [convention center construction] is not going over budget.
-- Music City Center Authority PR manager (former journo) Holly McCall
less than 10 months ago



Now, the Music city Center is way over budget; it'll have to pay $15 million more than it planned for this land. That cost is not in the budget of the project.
The spokesperson for the Music City Center, Holly McCall, said they'll have to do some number crunching. McCall said the Convention Center Authority will meet with the management team to assess the impact on the budget.


North End residents may recall that this is not the first time Holly McCall has failed her own word regarding convention center construction. A year ago she failed to follow through on a promise to Hope Gardens residents and other neighborhood leaders to release to the public the Metro lease for the Greyhound bus terminal, sending it instead only to CM Erica Gilmore. She had already admitted in a community meeting that she did not publicize the lease earlier to the affected community because she was not required to do so.

We've seen Ms. McCall's rather selective and convenient code of transparency when it comes to releasing information on convention center business. I have no doubt that her experience as a former journo will help her spin the budget overage such that earlier promises will appear not to be broken. And we are likely to get half-truths and carefully worded flackery that fails the nobler notion that public officials should be accountable for overspending public dollars.